FOI performance monitoring - January to June 2005
|
Under the Freedom of Information (Scotland) Act - section 60 - code of practice, the HIE network is required to report on its performance under the legislation. The facts and figures below provide some statistics which summarise our handling of information requests for the first half of 2005. The number of requests which the HIE Network received and logged during the period were:
(* From 1 July 2005, strategic alterations to the boundaries of two local enterprise companies resulted in the formation of HIE Moray and Inverness Nairn Badenoch and Strathspey Enterprise (INBSE). They replace Moray Badenoch and Strathspey Enterprise (MBSE) and Inverness and Nairn Enterprise (INE) respectively.) Average time to fully respond and close a request for information: 8 days The number of total refusals: 1 Reason for refusal: Information otherwise accessible The number of entire documents withheld and the reasons for their refusal: 15 documents were withheld from 7 requests Exemption category
The number of entire documents which were partially disclosed: 11 documents were partially disclosed from 6 requests
The number of entire documents which were fully published: 142 The number of requests where information was provided within response (ie the information was provided as part of the response but no additional documents were provided): 38 The number of requests where HIE did not have the information to disclose: 11 The number of requests presently suspended waiting clarification: 1 The number of requests suspended then closed (no clarification received): 2 The number of charges applied to requests: 0 The number of reviews: 2 The number of reviews upholding original decision: 2 The number of appeals with the Scottish Information Commissioner’s Office: 0 The number of instances when the time limit for reply has been exceeded and reasons: 0 Total number of visits to the web site's reading room:
Total number of documents downloaded from web site: 5,103 Most popular download: Summary response to EU draft audit of objective 1 programme 1994 to 1999 - 493 copies downloaded. |